BOSTON- SOMERVILLE- MEDFORD- STONEHAM- WOBURN- READING- HIGHWAY LIGHTING REHABILITATION ON I-93 (PHASE II)
This project updates and replaces the highway lighting system on Interstate 93 in the municipalities of Boston, Somerville, Medford, Stoneham, Woburn and Reading.
Location:
  • City of Boston
  • City of Medford
  • Town of Reading
  • City of Somerville
  • Town of Stoneham
  • City of Woburn
  • Construction Begins: Spring 2018
    Resident Engineer: Ahmad Rafieizadeh
    Construction Bid Price: $14,781,168.50
    District: District 4

    Contracts (1) Progress
    # 100297 -- Construction Contract
    Highway Lighting System Replacements and Improvements (Including ITS Camera System Installation) along a Section of Interstate 93 (Phase II). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/03/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/18/2017
    Project Need Form PNF Approved 01/18/2017
    Project Initiation Form PIF Entered 01/18/2017
    Project Initiation Form PRC Submitted 01/18/2017
    Project Review Committee PRC Approved 01/27/2017
    Project Status Advertised 04/29/2017
    Project Management
    100% Design 100% Package Received 03/22/2017
    Final Design PS&E Received 04/12/2017
    Final Design PS&E to FAPRO 04/18/2017