Project Description:
UPTON- RECONSTRUCTION OF HARTFORD AVENUE NORTH AND HIGH STREET (PHASE II)
The proposed work includes resurfacing and box widening of Hartford Avenue North and High Street, from the intersection of Route 140 to 500 feet west of the intersection of School Street and Westboro Road. Additional work includes installation of new signals and minor widening at the Route 140 intersection, reconstruction of existing sidewalks and construction of new sidewalks, drainage improvements, granite curbing and related work.
Location:
  • Town of Upton
  • Construction Begins: Autumn 2020
    Resident Engineer: Christopher Lee
    Construction Bid Price: $3,167,839.00
    District: District 3

    Contracts (1) Progress
    # 112695 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Hartford Avenue North, High and Main (Route 140) Streets (Phase 2) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/18/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/19/2017
    Project Initiation Form PIF Entered 01/19/2017
    Project Initiation Form PRC Submitted 05/11/2017
    Project Review Committee PRC Approved 06/06/2017
    Project Status Advertised 08/29/2020
    Project Management
    100% Design 100% Package Received 07/11/2019
    100% Design 100% Package Comments to DE 09/24/2019
    100% Design 100% Package Rejected 05/29/2019
    100% Design 100% Package Rejected 06/28/2019
    25% Design 25% Package Received 05/08/2012
    25% Design Design Public Hearing 10/22/2015
    75% Design 75% Package Received 08/18/2016
    Final Design PS&E Received 02/14/2020
    Final Design PS&E Received - Resub 1 04/02/2020
    Final Design PS&E Received - Resub 2 05/21/2020
    Final Design PS&E Received - Resub 3 07/27/2020
    Final Design PS&E Received - Resub 4 08/14/2020