Project Description:
PITTSFIELD- RESURFACING AND RELATED WORK ON MERRILL ROAD, INCLUDING CONSTRUCTION OF SHARED-USE PATH
This project proposes to resurface 0.85 mile of Merrill Road (Route 9) from East Street to Junction Road (approx. MM 1.78 to MM 2.63). The project will include some changes to pavement cross-slope to correct super-elevation deficiencies and improve curve banking. Drainage, guardrail, and other supporting elements will be evaluated for compliance with current design and safety standards. The existing sidewalk on the north side of Merrill Road, from East Street to Junction Road, will be replaced with a shared-use path to improve bike/ped accommodation along the corridor. This proposed shared use path will extend an additional 0.5 mile east of Junction Road to meet the proposed extension of the Ashuwillticook Rail Trail.
Location:
  • City of Pittsfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2028
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $14,473,273.40
    Estimated Total Federal Participating Construction Cost: $15,059,374.83
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: 25% Package Comments to DE (as of 04/16/2021 )

    Contracts (3) Progress
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 115801 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: PITTSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • AC 1 of 2; Total Project Cost = $16,866,500; YOE = 12%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $10,475,038.40
    State Cost: $2,618,759.60
    Total Cost: $13,093,798.00

    Planned Federal FY: 2029
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: PITTSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • AC 1 of 2; Total Project Cost = $16,866,500; YOE = 12%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,018,161.60
    State Cost: $754,540.40
    Total Cost: $3,772,702.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/01/2017
    Project Initiation Form PIF Entered 03/15/2017
    Project Initiation Form PRC Submitted 03/15/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Management
    25% Design 25% Package Received 01/11/2021
    25% Design 25% Package Comments to DE 04/16/2021
    Consultant Contract Process NTP Issued 10/24/2018