Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
STURBRIDGE- CLARK ROAD WATERLINE CONNECTION
Project consists of extending ductile iron town water line approx. 800 feet to neighborhood and connecting two residences to town water.
Location:
  • Town of Sturbridge
  • Construction Begins: Spring 2019
    Resident Engineer: David Windoloski
    Construction Bid Price: $231,561.43
    District: District 3

    Contracts (1) Progress
    # 106781 -- Construction Contract
    Installation of Water Main along Clark Road and Clark Road Extension Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/05/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/08/2017
    Project Initiation Form PIF Entered 06/22/2017
    Project Initiation Form PRC Submitted 06/22/2017
    Project Review Committee PRC Approved 07/20/2017
    Project Status Advertised 01/05/2019
    Project Management
    100% Design 100% Package Received 04/25/2018
    Final Design PS&E Received 12/27/2018
    Final Design PS&E to FAPRO 12/27/2018