Project Description:
SOUTHBRIDGE- INTERSECTION IMPROVEMENTS AT CENTRAL STREET, FOSTER STREET, HOOK STREET AND HAMILTON STREET
This project includes approximately 1,500-linear feet along Central Street, Hamilton Street, LaRochelle Way, Foster Street and Hook Street. The major improvements include intersection improvements at Hamilton Street/ Hook Street (mini roundabout), Central Street/ Hook Street/ Foster Street (closure of intersection), LaRochelle Way/ Central Street, and LaRochelle Way Extension/Foster Street. Roadway improvements include the addition of bicycle lanes, additional turn lanes at the proposed signalized intersection, converting a unsignalized intersection with a monument in the middle to mini roundabout, and making accommodations for a multi-use trail at the proposed traffic signal. The new traffic signal shall include the connection of a new roadway extension from Foster Street to Central Street directly across from LaRochelle Way. Reconstructed or new sidewalks are proposed throughout.
Location:
  • Town of Southbridge
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2025
    Project Manager: Kathy Dougherty
    Estimated Total Contract Cost: $8,140,713.91
    Estimated Total Federal Participating Construction Cost: $7,279,443.35
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: PS&E Received (as of 02/22/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: SOUTHBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, CMAQ + HSIP + STBG Total Project Cost = $7,279,443, Design Status = Final Design, PM Score = 14 out of 27
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $1,600,000.00
    State Cost: $400,000.00
    Total Cost: $2,000,000.00

    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: SOUTHBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, CMAQ + HSIP + STBG Total Project Cost = $7,279,443, Design Status = Final Design, PM Score = 14 out of 27
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $900,000.00
    State Cost: $100,000.00
    Total Cost: $1,000,000.00

    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: SOUTHBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, CMAQ + HSIP + STBG Total Project Cost = $7,279,443, Design Status = Final Design, PM Score = 14 out of 27
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,423,554.40
    State Cost: $855,888.60
    Total Cost: $4,279,443.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/14/2017
    Project Initiation Form PIF Entered 02/14/2017
    Project Initiation Form PRC Submitted 03/13/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Management
    100% Design 100% Package Received 07/11/2023
    25% Design 25% Package Received 09/17/2019
    25% Design 25% Package Comments to DE 12/26/2019
    25% Design 25% Package Approved 02/24/2021
    25% Design Design Public Hearing 04/01/2021
    75% Design 75% Package Received 12/21/2021
    75% Design 75% Package Comments to DE 04/15/2022
    Final Design PS&E Received 02/22/2024