Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LANCASTER- INTERSECTION IMPROVEMENTS ON ROUTE 117/ROUTE 70 AT LUNENBURG ROAD AND ROUTE 117/ROUTE 70 AT MAIN STREET
The proposed project will involve the installation of traffic signals and geometric improvements to the intersections of Route 117/Route 70 N (Lunenburg Road) and Route 117/Route 70 S (Main Street). In addition, approximately 0.23 miles of Route 117 between the two intersections will be part of the project. Regarding secondary assets, improvements are expected to be made to sidewalks, accessible ramps, pavement markings, signage and curbing within the project area. Incorporation of bike lanes in the project area will also provide safer and clearer routes for users.
Location:
  • Town of Lancaster
  • Construction Begins: Spring 2022
    Resident Engineer: Jeffrey Goyne
    Construction Bid Price: $4,193,535.89
    District: District 3

    Contracts (1) Progress
    # 117647 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) along a Section of Main Street (Route 70/117) at Lunenburg and Seven Bridge Roads Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/17/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/14/2017
    Project Initiation Form PIF Entered 02/14/2017
    Project Initiation Form PRC Submitted 03/13/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 03/26/2022
    Project Management
    100% Design 100% Package Received 11/11/2020
    100% Design 100% Package Comments to DE 02/23/2021
    25% Design 25% Package Received 09/27/2017
    25% Design 25% Package Comments to DE 03/12/2018
    25% Design Design Public Hearing 05/23/2018
    75% Design 75% Package Received 03/23/2020
    75% Design 75% Package Comments to DE 06/09/2020
    Final Design PS&E Received 08/18/2021
    Final Design PS&E to FAPRO 03/07/2022