Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SAUGUS- CULVERT REPLACEMENT & ENVIRONMENTAL REMEDIATION, WHEELABRATOR ACCESS DRIVE OVER CRESCENT MARSH/BEAR CREEK (MASSDOT OWNED)
The proposed project will replace an existing MassDOT-owned culvert conveying tidal flow and stormwater from the Crescent Marsh to the Bear Creek Estuary. The existing steel culvert is crushed under a capped landfill and requires replacement to restore tidal flow to Crescent Marsh and prevent contamination of the ACEC-designated Bear Creek estuary. The EPA and MassDEP have long expressed interest in the replacement of the culvert and are requesting MassDOT proceed with the design of the replacement to prevent regulatory action. However, any future substantial delays in progressing the project's development may result in substantial risk to MassDOT and may result in future enforcement actions from the regulatory agencies.
Location:
  • Town of Saugus
  • Construction Begins: Autumn 2019
    Resident Engineer: Robert Bosy
    Construction Bid Price: $2,035,156.07

    Contracts (1) Progress
    # 109102 -- Construction Contract
    Crescent Marsh Culvert Replacement under Unnamed Access Road to Wheelabrator Technologies Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/05/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/21/2017
    Project Initiation Form PIF Entered 02/21/2017
    Project Initiation Form PRC Submitted 02/21/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 07/27/2019
    Project Management
    25% Design 25% Package Received 06/14/2017
    75% Design 75% Package Received 03/07/2018
    Final Design PS&E Received 02/22/2018
    Final Design PS&E Received - Resub 1 05/31/2019