TEMPLETON- ROUNDABOUT CONSTRUCTION AT THE INTERSECTION OF PATRIOTS ROAD, SOUTH MAIN STREET, NORTH MAIN STREET AND GARDNER ROAD
The intersection of Patriots Road, South Main Street, North, Main Street and Gardner Road has experienced several safety concerns. This project is located in the Town center, and is a major regional connector roadway. The existing intersection is an unsignalized five legged intersection with several approaches marked with turn lanes. The preferred alternative would convert the five legged unsignalized intersection to a single-lane roundabout, resurface intersection approaches, and provide new pavement markings, sidewalks, wheelchair ramps and crosswalks.
Location:
  • Town of Templeton
  • Construction Begins: Spring 2023
    Resident Engineer: Alex Amadon
    Construction Bid Price: $2,251,718.06
    District: District 2

    Contracts (3) Progress
    # 115801 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 121400 -- Construction Contract
    Construction of a Roundabout at the Intersection of Patriots and Gardner Roads and North and South Main Streets 58% Complete
    # 77888 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/25/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/22/2017
    Project Initiation Form PIF Entered 02/22/2017
    Project Initiation Form PRC Submitted 02/24/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 02/11/2023
    Project Management
    100% Design 100% Package Received 05/18/2022
    25% Design 25% Package Received 04/25/2019
    25% Design 25% Package Comments to DE 07/25/2019
    25% Design Design Public Hearing 11/04/2020
    75% Design 75% Package Received 03/22/2021
    Final Design PS&E Received 12/09/2022
    Final Design PS&E to FAPRO 01/30/2023