TEMPLETON- ROUNDABOUT CONSTRUCTION AT THE INTERSECTION OF PATRIOTS ROAD, SOUTH MAIN STREET, NORTH MAIN STREET AND GARDNER ROAD
The intersection of Patriots Road, South Main Street, North, Main Street and Gardner Road has experienced several safety concerns. This project is located in the Town center, and is a major regional connector roadway. The existing intersection is an unsignalized five legged intersection with several approaches marked with turn lanes. The preferred alternative would convert the five legged unsignalized intersection to a single-lane roundabout, resurface intersection approaches, and provide new pavement markings, sidewalks, wheelchair ramps and crosswalks.
Location:
  • Town of Templeton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2023
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $1,866,653.94
    Estimated Total Federal Participating Construction Cost: $2,037,795.02
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 2
    Current Status: 75% Package Received (as of 03/22/2021 )

    Contracts (1) Progress
    # 77888 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: TEMPLETON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $1,375,559.20
    State Cost: $343,889.80
    Total Cost: $1,719,449.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/22/2017
    Project Initiation Form PIF Entered 02/22/2017
    Project Initiation Form PRC Submitted 02/24/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Management
    25% Design 25% Package Received 04/25/2019
    25% Design 25% Package Comments to DE 07/25/2019
    25% Design Design Public Hearing 11/04/2020