Project Description: |
SOUTH HADLEY- RECONSTRUCTION OF MAIN STREET, FROM THE CHICOPEE CITY LINE TO CANAL STREET (0.67 MILES)
This project consists of milling, resurfacing, and pavement widening on a section of Main Street in South Hadley from the Chicopee City Line to Canal Street. The work will include milling, resurfacing, new and reconstructed sidewalks, wheelchair ramps, bicycle lanes, pavement markings, and signage.
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Municipality |
Construction Begins: | Spring 2027 |
Project Manager: | Kathy Dougherty![]() |
Estimated Total Contract Cost: | $8,287,219.00 |
Estimated Total Federal Participating Construction Cost: | $7,888,044.35 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization. |
District: | District 2 |
Current Status: | 25% Package Received - Resub 1 (as of 04/08/2025 ) |
|
Bridges |
|
|
|