Project Description:
HOLYOKE- IMPROVEMENTS AT KELLY COMMUNITY SCHOOL (SRTS)
This projects includes the construction of pedestrian improvements at the intersection of Main Street and Appleton Street, including a full upgrade of all traffic signal equipment, the construction of bump-outs on all four corners of the intersection with ADA-complaint curb ramps, and crosswalk restriping. The project also includes lighting upgrades under the Appleton Street railroad bridge.
Location:
  • City of Holyoke
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Daniel Boucher
    Construction Bid Price: $801,795.10
    District: District 2

    Contracts (2) Progress
    # 109596 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along Sections of Main (Route 141), Appleton and Crescent Streets (Safe Routes to School – Kelly Community School) Completed
    # 77889 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/19/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2017
    Project Initiation Form PIF Entered 02/24/2017
    Project Initiation Form PRC Submitted 02/24/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 09/07/2019
    Project Management
    100% Design 100% Package Received 03/18/2019
    100% Design 100% Package Comments to DE 05/10/2019
    25% Design 25% Package Received 01/24/2018
    25% Design Design Public Hearing 01/08/2019
    75% Design 75% Package Received 01/24/2018
    75% Design 75% Package Comments to DE 04/06/2018
    Final Design PS&E Received 08/02/2019
    Final Design PS&E to FAPRO 08/26/2019