Project Description:
WINCHESTER- IMPROVEMENTS AT VINSON-OWEN ELEMENTARY SCHOOL (SRTS)
Project includes construction of sidewalks and bike lanes on Ridge Street from Johnson Road to Coolidge Street and the installation of a traffic signal at the intersection of Johnson Road and Ridge Street.
Location:
  • Town of Winchester
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Gennady Shkolnikov
    Construction Bid Price: $1,599,186.40
    District: District 4

    Contracts (2) Progress
    # 112793 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along Sections of Ridge Street and Johnson Road (Safe Routes to School - Vinson-Owen Elementary School) Completed
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/21/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2017
    Project Initiation Form PIF Entered 02/24/2017
    Project Initiation Form PRC Submitted 02/24/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 09/05/2020
    Project Management
    100% Design 100% Package Received 03/26/2020
    100% Design 100% Package Comments to DE 05/04/2020
    25% Design 25% Package Received 08/20/2018
    25% Design 25% Package Comments to DE 11/06/2018
    25% Design Design Public Hearing 09/19/2019
    75% Design 75% Package Received 03/06/2020
    75% Design 75% Package Comments to DE 05/04/2020
    Final Design PS&E Received 07/21/2020
    Final Design PS&E to FAPRO 08/31/2020