Project Description: |
WINCHESTER- IMPROVEMENTS AT VINSON-OWEN ELEMENTARY SCHOOL (SRTS)
Project includes construction of sidewalks and bike lanes on Ridge Street from Johnson Road to Coolidge Street and the installation of a traffic signal at the intersection of Johnson Road and Ridge Street.
|
Location: |
|
Construction Begins: | Winter 2020/2021 |
Resident Engineer: | Gennady Shkolnikov![]() |
Construction Bid Price: | $1,599,186.40 |
District: | District 4 |
Current Status: | All traffic equipment is hooked up and ready to be tested. Contractor is working on preparing for the final Surface Course. The Contractor has rebuilt the sidewalks which were in non-conformance and started working on punch list items. (as of 06/14/2022) |
|