Project Description:
NEWBURYPORT- IMPROVEMENTS AT NOCK MIDDLE SCHOOL & MOLIN UPPER ELEMENTARY SCHOOL (SRTS)
Project includes the installation of a High-intensity Activated crossWalk (HAWK) signal between Summit Place and Kent Street and corridor traffic calming measures along High Street (Routes 113) from Toppans Lane to Buck Street. Five-foot striped bike lanes in both directions along High Street, ADA-compliant ramps with perpendicular crossings, and new crosswalks and stopline pavement markings are also part of the project.
Location:
  • City of Newburyport
  • Construction Begins: Winter 2019/2020
    Resident Engineer: LauraBeth Webster
    Construction Bid Price: $2,041,506.95
    District: District 4

    Contracts (2) Progress
    # 109103 -- Construction Contract
    Sidewalk and ADA Improvements and Related Work (Including Signals) on a Section of High Street (Route 113) (Safe Routes to School – Nock Middle and Molin Upper Elementary Scho Completed
    # 85766 -- Design -- Highway
    Work will consist of providing school assessments and preliminary and final engineering design and construction phase services to the Highway Engineering Division for the 2014 Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/30/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2017
    Project Initiation Form PIF Entered 02/24/2017
    Project Initiation Form PRC Submitted 02/24/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 07/27/2019
    Project Management
    100% Design 100% Package Received 08/27/2018
    100% Design 100% Package Comments to DE 10/29/2018
    25% Design 25% Package Received 11/01/2017
    25% Design Design Public Hearing 06/14/2018
    75% Design 75% Package Received 11/01/2017
    75% Design 75% Package Comments to DE 04/25/2018
    Final Design PS&E Received 01/15/2019
    Final Design PS&E to FAPRO 07/12/2019