Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 6- ADA RETROFITS AT VARIOUS LOCATIONS
Location:
Construction Begins: Winter 2022/2023
Resident Engineer: Michael C. Haggerty
Construction Bid Price: $2,349,979.75
District: District 6

Contracts (3) Progress
# 115769 -- Design -- Services
Statewide - Master Service Agreement for design and review services. Final
# 120183 -- Construction Contract
Sidewalk and ADA Improvements at Various Locations 53% Complete
# 77866 -- Design -- Hwy Eng Open End
Master Service Agreement for statewide design and review services. Final

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/03/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/28/2017
    Project Initiation Form PIF Entered 03/02/2017
    Project Initiation Form PRC Submitted 03/02/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 09/10/2022
    Project Management
    100% Design 100% Package Received 05/21/2020
    100% Design 100% Package Comments to DE 06/30/2020
    25% Design 25% Package Received 08/12/2019
    75% Design 75% Package Received 08/12/2019
    75% Design 75% Package Received 12/18/2019
    75% Design 75% Package Comments to DE 01/14/2020
    Final Design PS&E Received 02/14/2022
    Final Design PS&E Received - Resub 1 04/29/2022
    Final Design PS&E Received - Resub 2 08/16/2022
    Final Design PS&E Received - Resub 3 08/26/2022