Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 6- ADA RETROFITS AT VARIOUS LOCATIONS
Location:
Construction Begins: Spring 2020
Resident Engineer: Maidul Islam
Construction Bid Price: $796,996.27
District: District 6

Contracts (2) Progress
# 109994 -- Construction Contract
Sidewalk and ADA Improvements at Various Locations Completed
# 77866 -- Design -- Hwy Eng Open End
Master Service Agreement for statewide design and review services. Final

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/01/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/28/2017
    Project Initiation Form PIF Entered 03/02/2017
    Project Initiation Form PRC Submitted 03/02/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 10/26/2019
    Project Management
    100% Design 100% Package Received 07/02/2019
    100% Design 100% Package Comments to DE 08/13/2019
    25% Design 25% Package Received 04/10/2019
    75% Design 75% Package Received 04/12/2019
    75% Design 75% Package Comments to DE 05/23/2019
    Final Design PS&E Received 09/26/2019
    Final Design PS&E to FAPRO 10/18/2019