Project Description:
BOSTON- ROADWAY RECONSTRUCTION CYPHER STREET, E STREET AND FARGO STREET
Project includes the reconstruction and extension of Cypher St from the South Boston Bypass Road to E Street as Phase 1. Further improvements along E Street and then from E Street realigned to Summer St, along with a potential land swap with Fargo Street as a Phase 2. Improvements include new roadway, sidewalks, crosswalks and signals. Design to accommodate Complete Streets criteria and maintain truck traffic.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $20,287,865.40
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: PS&E Received (as of 09/28/2022 )

    Contracts (2) Progress
    # 115784 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/01/2017
    Project Initiation Form PIF Entered 03/01/2017
    Project Initiation Form PRC Submitted 03/03/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Management
    100% Design 100% Package Received 10/01/2021
    100% Design 100% Package Comments to DE 12/02/2021
    25% Design 25% Package Received 08/16/2018
    25% Design 25% Package Comments to DE 10/09/2018
    25% Design Design Public Hearing 11/13/2018
    75% Design 75% Package Received 11/15/2019
    75% Design 75% Package Comments to DE 03/06/2020
    Final Design PS&E Received 09/28/2022