Project Description:
LAWRENCE- NORTH ANDOVER- RESURFACING AND RELATED WORK ON ROUTE 114
The project begins at mile marker 2.84 in North Andover and extends westerly along State Route 114 to mile marker 1.9 in Lawrence for a distance of .95 miles. Roadway work shall consist of curb to curb micromilling and resurfacing with Superpave Surface Course of Route 114 in North Andover and Lawrence within the limits outlined above. Related work includes upgrading existing guardrail within the project limits; constructing wheelchair ramps, sidewalks, and driveway aprons; adjusting, cleaning and rebuilding drainage structures; replacing frames and grates with lock down castings; removing and resetting granite curb; tree trimming; pavement markings and slotted pavement markers; and traffic signal modifications at Haverhill St., Eaglewood Shops, and Waverly Road; and incidental items of work.
Location:
  • City of Lawrence
  • Town of North Andover
  • Construction Begins: Winter 2018/2019
    Resident Engineer: John Mitchell
    Construction Bid Price: $1,568,816.79
    District: District 4

    Contracts (1) Progress
    # 105492 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 114 (Turnpike Street) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/15/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/01/2017
    Project Initiation Form PIF Entered 03/01/2017
    Project Initiation Form PRC Submitted 03/01/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 08/11/2018
    Project Management
    100% Design 100% Package Received 04/06/2018
    100% Design 100% Package Comments to DE 05/10/2018
    75% Design 75% Package Received 01/09/2018
    Final Design PS&E Received 06/08/2018
    Final Design PS&E Received - Resub 1 07/16/2018