Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LANESBOROUGH- RESURFACING AND RELATED WORK ON ROUTE 7
The work under this Contract includes, but is not limited to, clearing and grubbing; full depth construction; reclamation; milling; paving; constructing driveways; cement concrete sidewalks and wheelchair ramps; extending a twin 36” RCP culvert and construction of a replacement concrete headwall; landscaping; installing new granite curbing and HMA berm; installing highway guardrail; new stormwater drainage pipes and structures; fencing; providing and spreading loam borrow and seed; tree trimming; traffic signals; traffic signing and pavement markings; traffic control management and other street improvements. Work also includes replacement of guardrail; tree removal and clearing vegetation; installing traffic management safety signing, placing erosion control measures as required; grading and compacting; reconstructing driveways; relocation of utility poles and overhead wires; relocation of a water main; shrubs within the Project’s Right-of-Way; and other incidental items required to complete the work as shown on the Plans, as specified herein, and as required by the Engineer.
Location:
  • Town of Lanesborough
  • Construction Begins: Autumn 2023
    Resident Engineer: Michael Wall
    Construction Bid Price: $7,204,385.00
    District: District 1

    Contracts (3) Progress
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 123873 -- Construction Contract
    Resurfacing and Related Work on Route 7
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/16/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2017
    Project Initiation Form PIF Entered 03/02/2017
    Project Initiation Form PRC Submitted 03/02/2017
    Project Review Committee PRC Approved 03/28/2017
    Project Status Advertised 08/26/2023
    Project Management
    100% Design 100% Package Received 08/29/2022
    100% Design 100% Package Comments to DE 10/25/2022
    100% Design 100% Package Comments to DE 03/15/2023
    100% Design 100% Package Received - Resub 1 02/06/2023
    100% Design 100% Package Received - Resub 3 06/13/2023
    25% Design 25% Package Received 06/11/2020
    25% Design 25% Package Comments to DE 09/21/2020
    25% Design Design Public Hearing 05/13/2021
    75% Design 75% Package Received 09/10/2021
    75% Design 75% Package Comments to DE 12/13/2021
    Final Design PS&E Received 06/30/2023
    Final Design PS&E Received - Resub 1 07/28/2023
    Consultant Contract Process NTP Issued 05/16/2019