Project Description:
SPENCER- RESURFACING AND RELATED WORK ON ROUTE 9
The project consists of resurfacing and related work on approximately 1.00 mile of Route 9 from just east of the Route 49 intersection to just west of the Water Street/Sumner Street intersection in the town of Spencer, Massachusetts. A combination of full depth pavement reconstruction with pavement mill and overlay is proposed. The work includes traffic signal reconstruction, pavement milling and overlay, full depth pavement reconstruction, roadway widening, sidewalk and shared use path construction, drainage structure and pipe installation, hydrant relocation, guardrail installation, traffic signing and pavement markings, proposed water main, improvements to the bridge over Seven Mile River, emergency pre-emption traffic control signal at the Spencer Fire and Police Departments, and other street improvements.
Location:
  • Town of Spencer
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2024
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $10,195,366.65
    Estimated Total Federal Participating Construction Cost: $10,136,437.75
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: PS&E Received - Resub 2 (as of 03/20/2024 )

    Contracts (1) Progress
    # 77851 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: SPENCER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $9,350,178, Design Status = 75%
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $7,480,142.40
    State Cost: $1,870,035.60
    Total Cost: $9,350,178.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2017
    Project Initiation Form PIF Entered 03/02/2017
    Project Initiation Form PRC Submitted 03/02/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Management
    100% Design 100% Package Received 07/20/2023
    100% Design 100% Package Comments to DE 08/22/2023
    25% Design 25% Package Received 08/04/2021
    25% Design 25% Package Comments to DE 05/31/2022
    25% Design 25% Package Received - Resub 1 04/25/2022
    25% Design Design Public Hearing 01/05/2023
    75% Design 75% Package Received 03/09/2023
    75% Design 75% Package Comments to DE 04/10/2023
    Final Design PS&E Received 01/22/2024
    Final Design PS&E Received - Resub 1 02/27/2024
    Final Design PS&E Received - Resub 2 03/20/2024
    Consultant Contract Process NTP Issued 05/29/2019