Project 608815
(Click here for a glossary of terms)
Project Description:
HOLDEN- RESURFACING AND RELATED WORK ON ROUTE 122A
Location:
Town of Holden
Construction Begins:
Spring 2022
Resident Engineer:
Linda Terry
Construction Bid Price:
$2,615,305.07
District:
District 3
Contracts
(1)
Progress
# 117602 -- Construction Contract
Resurfacing and Related Work on a Section of Route 122A (Main Street)
Completed
Bridges
G08002
details...
G08030
details...
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Contract Dates
Notice to Proceed:
05/17/2022
Contract Information
Project Designer:
In-House Boston
Funding Source:
NATIONAL HIGHWAY SYSTEM
Construction Progress
Milestone Details
TIP/Funding
Project Issues
See the Milestone Details tab for additional Project information
Initiation
no comments
Scoping
no comments
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
Construction Progress
Milestone Details
TIP/Funding
Project Issues
TIP Lines for
2025 - 2029
No TIP Data Available For This Project
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Project Task Information
Project Status
Project Need Form
PNF Entered
03/02/2017
Project Initiation Form
PIF Entered
03/02/2017
Project Initiation Form
PRC Submitted
03/02/2017
Project Review Committee
PRC Approved
03/23/2017
Project Status
Advertised
03/19/2022
Project Management
100% Design
100% Package Received
12/21/2021
25% Design
25% Package Received
09/11/2018
25% Design
25% Package Received - Resub 1
03/18/2021
75% Design
75% Package Received
09/11/2018
75% Design
75% Package Comments to DE
12/27/2018
75% Design
75% Package Received - Resub 1
03/18/2021
Final Design
PS&E Received
02/18/2022
Final Design
PS&E to FAPRO
03/07/2022