Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SALEM- LYNN- RESURFACING AND RELATED WORK ON ROUTE 107
Location:
  • City of Lynn
  • City of Salem
  • Construction Begins: Spring 2021
    Resident Engineer: Michael Cannata
    Construction Bid Price: $3,412,892.90
    District: District 4
    Current Status: All field work is complete. (as of 12/19/2023)

    Contracts (1) Progress
    # 114228 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 107 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/02/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    All field work is complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2017
    Project Initiation Form PIF Entered 03/02/2017
    Project Initiation Form PRC Submitted 03/02/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 03/27/2021
    Project Management
    75% Design 75% Package Received 10/24/2020
    75% Design 75% Package Comments to DE 11/30/2020
    Final Design PS&E Received 02/02/2021
    Final Design PS&E to FAPRO 03/15/2021