Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DANVERS- MIDDLETON- RESURFACING AND RELATED WORK ON ROUTE 114
The work under this contract consists of excavation; full depth widening less than 4’; pavement fine milling; paving; constructing driveways, hot mix asphalt sidewalks & driveways, pedestrian curb ramps; removing and resetting existing granite curb and edging; installing new granite curb and edging; reconstruction of drainage systems; reconstruction of water lines; tree trimming; landscaping; providing and spreading loam borrow and seed; installation of traffic signal equipment, traffic signing and pavement markings, traffic control management, and other street improvements. The work also includes coordination with utility pole relocations, and other utility relocation work. The work also consists of the reconstruction of traffic signal systems at two (2) locations, complete with vehicle detection, emergency vehicle preemption, signal posts, signal heads, mast arm assemblies, cabinets, foundations, pull boxes, electric handholes, service connections, and all other equipment, materials and incidental costs necessary to furnish, install and program a complete and functioning traffic control signal system as specified and as shown in the contract documents.
Location:
  • Town of Danvers
  • Town of Middleton
  • Construction Begins: Summer 2023
    Resident Engineer: Max Caron
    Construction Bid Price: $4,371,022.69
    District: District 4
    Current Status: Contractor begins saw cutting for upcoming drainage and signal work at the intersection of Watson Parkway & Rt. 114. (as of 02/02/2024)

    Contracts (2) Progress
    # 122001 -- Construction Contract
    Resurfacing and Related Work on Route 114 12% Complete
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 07/03/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractor begins saw cutting for upcoming drainage and signal work at the intersection of Watson Parkway & Rt. 114.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2017
    Project Initiation Form PIF Entered 03/02/2017
    Project Initiation Form PRC Submitted 03/02/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 05/06/2023
    Project Management
    100% Design 100% Package Received 11/23/2022
    25% Design 25% Package Received 01/21/2022
    25% Design 25% Package Comments to DE 02/22/2022
    75% Design 75% Package Received 06/30/2022
    75% Design 75% Package Comments to DE 09/30/2022
    Final Design PS&E Received 03/21/2023
    Final Design PS&E to FAPRO 04/24/2023