RAYNHAM- BRIDGEWATER- WEST BRIDGEWATER- BROCKTON- PAVEMENT PRESERVATION AND RELATED WORK ON ROUTE 24
Location:
  • Town of Bridgewater
  • City of Brockton
  • Town of Raynham
  • Town of West Bridgewater
  • Construction Begins: Summer 2020
    Resident Engineer: Alfredo Nunez
    Construction Bid Price: $15,387,893.85
    District: District 5
    Current Status: • Awaiting directions on exposed concrete deck patches texturing before a Final Inspection. • Preliminary Punch List work was completed on 11/20/23. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. (as of 03/21/2024)

    Contracts (1) Progress
    # 111312 -- Construction Contract
    Resurfacing and Related Work (Including 6 Bridge Decks and Ramps) along a Section of Route 24 (Fall River Expressway) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 09/17/2020
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    • Awaiting directions on exposed concrete deck patches texturing before a Final Inspection. • Preliminary Punch List work was completed on 11/20/23. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2017
    Project Initiation Form PIF Entered 03/02/2017
    Project Initiation Form PRC Submitted 03/02/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 05/09/2020
    Project Management
    100% Design 100% Package Received 01/24/2020
    25% Design 25% Package Received 08/26/2019
    75% Design 75% Package Received 08/26/2019
    75% Design 75% Package Comments to DE 09/26/2019
    Final Design PS&E Received 01/24/2020
    Final Design PS&E to FAPRO 02/03/2020