Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WELLESLEY- NEWTON- WESTON- PAVEMENT RESURFACING AND RELATED WORK ON I-95
Location:
  • City of Newton
  • Town of Wellesley
  • Town of Weston
  • Construction Begins: Autumn 2018
    Resident Engineer: Paul Brennan
    Construction Bid Price: $6,521,953.10
    District: District 6

    Contracts (1) Progress
    # 103088 -- Construction Contract
    Resurfacing and Related Work along a Section of Interstate 95 (NB & SB). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/01/2018
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2017
    Project Initiation Form PIF Entered 03/02/2017
    Project Initiation Form PRC Submitted 03/02/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 12/30/2017
    Project Management
    100% Design 100% Package Received 12/11/2017
    25% Design 25% Package Received 11/07/2017
    25% Design 25% Package Comments to DE 12/04/2017
    75% Design 75% Package Received 11/07/2017
    75% Design 75% Package Comments to DE 12/04/2017
    Final Design PS&E Received 12/15/2017
    Final Design PS&E to FAPRO 12/18/2017