Project Description: |
ATTLEBORO- PAVEMENT PRESERVATION AND RELATED WORK ON I-95
|
Location: |
|
Construction Begins: | Summer 2019 |
Resident Engineer: | Eric Borman![]() |
Construction Bid Price: | $8,295,865.49 |
District: | District 5 |
Current Status: | Field operations complete, punch list work remains, no scheduled impacts to traffic. Scheduled work hours are Sunday thru Thursday, 8:00 PM to 5:00 AM. Expect periodic lane closures and restrictions. (as of 07/18/2025) |
Additional Info: | Single lane taking if needed. (as of 07/18/2025) |
|