Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NORTH ATTLEBOROUGH- ATTLEBORO- INTERSTATE MAINTENANCE AND RELATED WORK ON I-295
Location:
  • City of Attleboro
  • Town of North Attleborough
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Zachary D Veaner
    Estimated Total Contract Cost: $8,293,600.00
    Estimated Total Federal Participating Construction Cost: $8,542,920.00
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: ATTLEBORO
    NORTH ATTLEBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - Interstate Maintenance
    Federal Cost: $8,262,777.60
    State Cost: $918,086.40
    Total Cost: $9,180,864.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2017
    Project Initiation Form PIF Entered 03/02/2017
    Project Initiation Form PRC Submitted 03/02/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Management