Project Description: |
WESTFORD- BRIDGE REHABILITATION BEAVER BROOK ROAD OVER BEAVER BROOK (W-26-014)
The proposed project includes replacing the existing, deteriorated twin 90” CMP culverts carrying Beaver Brook Road over Beaver Brook. The twin CMP culverts will be replaced with a precast concrete bridge structure. There will be precast wingwalls adjacent to the bridge at both elevations.
|
Location: |
|
Construction Begins: | Summer 2022 |
Resident Engineer: | Christopher Deloge |
Construction Bid Price: | $2,510,870.00 |
District: | District 3 |
|
Bridges
|
|
|
|
|