NANTUCKET- IMPROVEMENTS ON MILESTONE ROAD
This project was developed as a rural road highway safety improvement project. A roadway safety audit was held to identify safety improvements along the corridor. Scope of work involves signing and striping, reconstruction of WCR’s and the potential of minor re-alignment of three intersections on Milestone Road.
Location:
  • Town of Nantucket
  • Construction Begins: Autumn 2018
    Resident Engineer: Michael Zuzevich
    Construction Bid Price: $3,268,888.00
    District: District 5

    Contracts (2) Progress
    # 104671 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Milestone Road Completed
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/29/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/07/2017
    Project Initiation Form PIF Entered 03/07/2017
    Project Initiation Form PRC Submitted 03/07/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 06/30/2018
    Project Management
    25% Design 25% Package Received 12/20/2017
    25% Design Design Public Hearing 03/27/2018
    75% Design 75% Package Received 12/20/2017
    75% Design 75% Package Comments to DE 02/01/2018
    Final Design PS&E Received 05/21/2018
    Final Design PS&E to FAPRO 06/18/2018