Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MEDFORD- IMPROVEMENTS AT BROOKS ELEMENTARY SCHOOL (SRTS)
This project expands upon Medford's Complete Streets project on High Street, focusing on the area of High Street between Auburn Street and Woburn Street to provide curb extensions and uniform bicycle treatments. This project also includes the relocation of the existing MBTA bus stop on the northeasterly side of the High Street/Mystic Street intersection to the northwesterly side of the intersection.
Location:
  • City of Medford
  • Construction Begins: Summer 2020
    Resident Engineer: Fred Collins
    Construction Bid Price: $781,641.00
    District: District 4

    Contracts (2) Progress
    # 111660 -- Construction Contract
    Sidewalk and ADA Improvements and Related Work (Including Flashing Beacons) along a Section of High Street (Route 60) (Safe Routes to School – Brooks Elementary School) Completed
    # 85766 -- Design -- Highway
    Work will consist of providing school assessments and preliminary and final engineering design and construction phase services to the Highway Engineering Division for the 2014 Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/24/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/10/2017
    Project Initiation Form PIF Entered 03/10/2017
    Project Initiation Form PRC Submitted 03/13/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 06/20/2020
    Project Management
    100% Design 100% Package Received 08/14/2019
    100% Design 100% Package Comments to DE 10/17/2019
    25% Design 25% Package Received 11/28/2017
    25% Design 25% Package Comments to DE 03/15/2018
    25% Design Design Public Hearing 05/29/2019
    75% Design 75% Package Received 11/28/2017
    75% Design 75% Package Comments to DE 03/15/2018
    Final Design PS&E Received 03/25/2020
    Final Design PS&E Received - Resub 1 05/22/2020