MONSON- BRIDGE REPLACEMENT, M-27-015, OLD WALES ROAD OVER CONANT BROOK
Location:
  • Town of Monson
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2024
    Project Manager: Harry Adolphe
    Estimated Total Contract Cost: $3,878,765.94
    Estimated Total Federal Participating Construction Cost: $4,298,663.34
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 04/27/2024 )

    Contracts (1) Progress
    # 77877 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: MONSON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $3,167,043.20
    State Cost: $791,760.80
    Total Cost: $3,958,804.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/20/2017
    Project Initiation Form PIF Entered 03/20/2017
    Project Initiation Form PRC Submitted 03/20/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 04/27/2024
    Project Management
    100% Design 100% Package Received 03/21/2022
    100% Design 100% Package Comments to DE 06/24/2022
    100% Design 100% Package Received - Resub 1 02/13/2023
    25% Design 25% Package Received 12/10/2019
    25% Design 25% Package Comments to DE 03/13/2020
    25% Design 25% Package Approved 03/31/2021
    25% Design Design Public Hearing 05/10/2021
    75% Design 75% Package Received 09/27/2021
    75% Design 75% Package Comments to DE 12/28/2021
    Final Design PS&E Received 10/23/2023
    Final Design PS&E Received - Resub 1 02/12/2024