Project Description:
WALES- BRIDGE REPLACEMENT, W-02-002, HOLLAND ROAD OVER WALES BROOK
The work under this Contract includes, but is not limited to, full-depth roadway construction; pavement fine milling; paving; constructing driveways; cement concrete sidewalks and pedestrian curb ramps; replacement of existing Bridge No.W-02-002 (17U) with a precast concrete rigid frame; utility pole service connection; clearing and grubbing; landscaping; grading and compacting; installing new granite curbing; installing highway guardrail; new drainage pipes and structures; new level spreader, fencing; placing erosion control measures as required; providing and spreading loam borrow and seed; tree trimming and removal; traffic signing and pavement markings; traffic control management and other street improvements; and other incidental costs required to complete the work as shown on the Plans, as specified herein, and as required by the Engineer.
Location:
  • Town of Wales
  • Construction Begins: Summer 2023
    Resident Engineer: Bailey Powers
    Construction Bid Price: $3,256,045.40
    District: District 2

    Contracts (3) Progress
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 122599 -- Construction Contract
    Bridge Replacement, W-02-002, Holland Road Over Wales Brook Completed
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/18/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/20/2017
    Project Initiation Form PIF Entered 03/20/2017
    Project Initiation Form PRC Submitted 03/20/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 06/24/2023
    Project Management
    100% Design 100% Package Received 10/25/2021
    25% Design 25% Package Received 08/04/2020
    25% Design 25% Package Comments to DE 10/07/2020
    25% Design Design Public Hearing 03/10/2021
    75% Design 75% Package Received 05/28/2021
    75% Design 75% Package Comments to DE 07/28/2021
    Final Design PS&E Received 06/23/2022
    Final Design PS&E Received - Resub 1 09/23/2022
    Final Design PS&E Received - Resub 2 02/22/2023
    Final Design PS&E Received - Resub 3 03/24/2023
    Final Design PS&E Received - Resub 4 05/03/2023