Project Description: |
HARDWICK- NEW BRAINTREE- BRIDGE REPLACEMENT, H-08-003=N-07-002, CREAMERY ROAD OVER WARE RIVER
This proposed bridge project consists of a 100’ long single span bridge. The bridge will increase the total curb-to-curb width to 14’ and an architecturally styled concrete bridge railing system will be located along both sides of the bridge with a steel highway guard railing located on both sides of both approaches. The roadway will be raised approximately 2’ to provide for hydraulic clearances which will require approximately 200’ of roadway improvements along both sides of the bridge. No pedestrian or bicycle accommodation improvements will be provided.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Construction Begins: | Autumn 2024 |
Project Manager: | William F Brown |
Estimated Total Contract Cost: | $4,133,055.64 |
Estimated Total Federal Participating Construction Cost: | $4,500,424.28 |
Funding Provision: | This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization. |
District: | District 2 |
Current Status: | PS&E Received - Resub 1 (as of 02/21/2024 ) |
|