ROWE- SUPERSTRUCTURE REPLACEMENT, R-10-008, CYRUS STAGE ROAD OVER POTTER BROOK
The purpose of this project is to replace the bridge carrying Cyrus Stage Road over Potter Brook. The project includes replacement of the superstructure, deck, and related elements. The project also includes bridge rail, guardrail, and roadway approach work. Necessary utility pole relocations are also included.
Location:
  • Town of Rowe
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2024
    Project Manager: Christopher I Cameron
    Estimated Total Contract Cost: $2,475,189.00
    Estimated Total Federal Participating Construction Cost: $2,779,505.02
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 1
    Current Status: PS&E Received (as of 04/16/2024 )

    Contracts (1) Progress
    # 101634 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide and bridge projects, for the purpose of maintaining Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: ROWE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $1,824,821.60
    State Cost: $456,205.40
    Total Cost: $2,281,027.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2017
    Project Initiation Form PIF Entered 03/21/2017
    Project Initiation Form PRC Submitted 03/21/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Management
    100% Design 100% Package Received 02/01/2024
    100% Design 100% Package Comments to DE 03/01/2024
    25% Design 25% Package Received 07/30/2020
    25% Design 25% Package Comments to DE 11/02/2020
    25% Design 25% Package Received - Resub 1 02/12/2021
    25% Design 25% Package Received - Resub 2 03/19/2021
    25% Design Design Public Hearing 06/01/2021
    75% Design 75% Package Received 12/22/2022
    75% Design 75% Package Comments to DE 02/06/2023
    Final Design PS&E Received 04/16/2024