OTIS- BRIDGE REPLACEMENT, O-05-007, TANNERY ROAD OVER W. BRANCH OF FARMINGTON RIVER
Location:
  • Town of Otis
  • Construction Begins: Winter 2021/2022
    Resident Engineer: Hugo Pacheco
    Construction Bid Price: $1,479,371.78
    District: District 1

    Contracts (3) Progress
    # 115778 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 117037 -- Construction Contract
    Bridge Replacement Br. No. O-05-007 (Pre-Stressed Concrete Deck Beams) Tannery Road over the West Branch Farmington River Completed
    # 77874 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/09/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2017
    Project Initiation Form PIF Entered 03/21/2017
    Project Initiation Form PRC Submitted 03/21/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 12/25/2021
    Project Management
    100% Design 100% Package Received 09/23/2020
    100% Design 100% Package Comments to DE 11/23/2020
    100% Design 100% Package Received - Resub 1 01/11/2021
    100% Design 100% Package Received - Resub 2 03/31/2021
    25% Design 25% Package Received 06/17/2019
    25% Design 25% Package Comments to DE 09/18/2019
    25% Design Design Public Hearing 01/14/2020
    75% Design 75% Package Received 05/15/2020
    Final Design PS&E Received 07/08/2021
    Final Design PS&E Received - Resub 1 11/10/2021
    Final Design PS&E Received - Resub 2 11/22/2021