CHESHIRE- BRIDGE REPLACEMENT, C-10-002, SAND MILL ROAD OVER DRY BROOK
.
Location:
  • Town of Cheshire
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2024
    Project Manager: Caitlin A Marshall
    Estimated Total Contract Cost: $3,486,888.40
    Estimated Total Federal Participating Construction Cost: $3,926,707.33
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: This project has been advertised for construction bids. (as of 03/16/2024 )

    Contracts (2) Progress
    # 115801 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77888 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: CHESHIRE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Increased from 2,405,358.00 to 3,926,707 01 via STIP Action 3.
  • Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $3,141,365.60
    State Cost: $785,341.40
    Total Cost: $3,926,707.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2017
    Project Initiation Form PIF Entered 03/21/2017
    Project Initiation Form PRC Submitted 03/21/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 03/16/2024
    Project Management
    100% Design 100% Package Received 08/30/2023
    25% Design 25% Package Received 10/25/2021
    25% Design Design Public Hearing 03/10/2022
    75% Design 75% Package Received 11/18/2022
    75% Design 75% Package Comments to DE 01/23/2023
    Final Design PS&E Received 08/30/2023
    Final Design PS&E Received - Resub 1 10/24/2023
    Final Design PS&E Received - Resub 2 12/13/2023
    Final Design PS&E Received - Resub 3 01/10/2024