Project Description:
CHARLEMONT- BRIDGE REPLACEMENT, C-05-042, EAST OXBOW ROAD OVER OXBOW BROOK
Location:
  • Town of Charlemont
  • Construction Begins: Spring 2024
    Resident Engineer: Niroj Bhattarai
    Construction Bid Price: $3,342,928.50
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 1

    Contracts (3) Progress
    # 102481 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide road and bridge projects, for the purpose of mainta Final
    # 125266 -- Construction Contract
    Bridge Replacement, C-05-042, East Oxbow Road over Oxbow Brook
    # 77851 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/08/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: CHARLEMONT
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $3,700,527.20
    State Cost: $925,131.80
    Total Cost: $4,625,659.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2017
    Project Initiation Form PIF Entered 03/21/2017
    Project Initiation Form PRC Submitted 03/21/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 02/17/2024
    Project Management
    100% Design 100% Package Received 03/10/2023
    100% Design 100% Package Comments to DE 04/13/2023
    25% Design 25% Package Received 01/27/2020
    25% Design 25% Package Received 11/22/2021
    25% Design 25% Package Comments to DE 12/23/2021
    25% Design Design Public Hearing 04/05/2022
    75% Design 75% Package Received 10/07/2022
    75% Design 75% Package Comments to DE 12/12/2022
    Final Design PS&E Received 06/09/2023
    Final Design PS&E Received - Resub 1 09/14/2023
    Final Design PS&E Received - Resub 2 10/05/2023
    Consultant Contract Process NTP Issued 08/02/2022