Project Description:
CHARLEMONT- BRIDGE REPLACEMENT, C-05-042, EAST OXBOW ROAD OVER OXBOW BROOK
Location:
  • Town of Charlemont
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2024
    Project Manager: Shahpar Negah
    Estimated Total Contract Cost: $4,383,594.11
    Estimated Total Federal Participating Construction Cost: $4,625,658.93
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 1
    Current Status: 75% Package Comments to DE (as of 12/12/2022 )

    Contracts (2) Progress
    # 102481 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide road and bridge projects, for the purpose of mainta Final
    # 77851 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: CHARLEMONT
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $3,795,893.00
    State Cost: $0.00
    Total Cost: $3,795,893.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2017
    Project Initiation Form PIF Entered 03/21/2017
    Project Initiation Form PRC Submitted 03/21/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Management
    25% Design 25% Package Received 01/27/2020
    25% Design 25% Package Received 11/22/2021
    25% Design 25% Package Comments to DE 12/23/2021
    75% Design 75% Package Received 10/07/2022
    75% Design 75% Package Comments to DE 12/12/2022