Project Description:
PITTSFIELD- BRIDGE REPLACEMENT, P-10-055, EAST NEW LENOX ROAD OVER SACKETT BROOK
Location:
  • City of Pittsfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2022
    Project Manager: John Fallon
    Estimated Total Contract Cost: $3,230,986.42
    Estimated Total Federal Participating Construction Cost: $3,634,790.47
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: PS&E Received (as of 06/24/2021 )

    Contracts (1) Progress
    # 77848 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: PITTSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $2,435,522.40
    State Cost: $608,880.60
    Total Cost: $3,044,403.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2017
    Project Initiation Form PIF Entered 03/21/2017
    Project Initiation Form PRC Submitted 03/21/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Management
    100% Design 100% Package Received 03/24/2021
    25% Design 25% Package Received 07/23/2019
    25% Design Design Public Hearing 02/20/2020
    75% Design 75% Package Received 10/19/2020
    Final Design PS&E Received 06/24/2021