Project Description:
STONEHAM- WINCHESTER- DECK REPLACEMENT, S-27-008=W-40-030 (2M5), MARBLE STREET OVER I-93
Scope of work will include deck replacement, adjustment of bearings and traffic safety upgrades.
Location:
  • Town of Stoneham
  • Town of Winchester
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Alyson Bedard
    Estimated Total Contract Cost: $3,286,074.50
    Estimated Total Federal Participating Construction Cost: $3,573,558.00
    District: District 4
    Current Status: 100% Package Comments to DE (as of 01/26/2021 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/31/2017
    Project Initiation Form PIF Entered 03/31/2017
    Project Initiation Form PRC Submitted 03/31/2017
    Project Review Committee PRC Approved 07/20/2017
    Project Management
    100% Design 100% Package Received 11/04/2020
    100% Design 100% Package Comments to DE 01/26/2021