Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
STONEHAM- WINCHESTER- DECK REPLACEMENT, S-27-008=W-40-030 (2M5), MARBLE STREET OVER I-93
Scope of work will include deck replacement, adjustment of bearings and traffic safety upgrades.
Location:
  • Town of Stoneham
  • Town of Winchester
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Genesis Poz Diaz
    Estimated Total Contract Cost: $2,644,190.00
    Estimated Total Federal Participating Construction Cost: $2,884,571.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: STONEHAM
    WINCHESTER
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $2,858,846.40
    State Cost: $714,711.60
    Total Cost: $3,573,558.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/31/2017
    Project Initiation Form PIF Entered 03/31/2017
    Project Initiation Form PRC Submitted 03/31/2017
    Project Review Committee PRC Approved 07/20/2017
    Project Management