STONEHAM- WINCHESTER- DECK REPLACEMENT, S-27-008=W-40-030 (2M5), MARBLE STREET OVER I-93
Scope of work will include deck replacement, adjustment of bearings and traffic safety upgrades.
Location:
  • Town of Stoneham
  • Town of Winchester
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2025
    Project Manager: Genesis Poz Diaz
    Estimated Total Contract Cost: $2,644,190.00
    Estimated Total Federal Participating Construction Cost: $2,884,571.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: STONEHAM
    WINCHESTER
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $2,858,846.40
    State Cost: $714,711.60
    Total Cost: $3,573,558.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/31/2017
    Project Initiation Form PIF Entered 03/31/2017
    Project Initiation Form PRC Submitted 03/31/2017
    Project Review Committee PRC Approved 07/20/2017
    Project Management