Project Description:
NORTHAMPTON- BRIDGE REPLACEMENT, N-19-068, OLD SPRINGFIELD ROAD OVER THE MILL RIVER
Location:
  • City of Northampton
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2025
    Project Manager: Caitlin A Marshall
    Estimated Total Contract Cost: $7,414,180.80
    Estimated Total Federal Participating Construction Cost: $7,760,399.47
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: 75% Package Received (as of 04/17/2024 )

    Contracts (1) Progress
    # 101635 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide and bridge projects, for the purpose of maintaining Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTHAMPTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $5,717,174.00
    State Cost: $0.00
    Total Cost: $5,717,174.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/18/2017
    Project Initiation Form PIF Entered 04/18/2017
    Project Initiation Form PRC Submitted 04/18/2017
    Project Review Committee PRC Approved 05/16/2017
    Project Management
    25% Design 25% Package Received 04/08/2022
    25% Design Design Public Hearing 10/18/2023
    75% Design 75% Package Received 04/17/2024