Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SPENCER- ROADWAY REHABILITATION OF MEADOW ROAD
The proposed project involves the reconstruction of Meadow Road, widening for bike accommodation, construction of new pedestrian sidewalks, transit accommodations, traffic safety, and drainage and stormwater quality improvements.
Location:
  • Town of Spencer
  • Construction Begins: Summer 2023
    Resident Engineer: Peter Kurt
    Construction Bid Price: $8,879,315.30
    District: District 3

    Contracts (1) Progress
    # 122515 -- Construction Contract
    Roadway Rehabilitation of Meadow Road 43% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/12/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/23/2017
    Project Initiation Form PIF Entered 07/12/2017
    Project Initiation Form PRC Submitted 07/13/2017
    Project Review Committee PRC Approved 07/20/2017
    Project Status Advertised 06/17/2023
    Project Management
    100% Design 100% Package Received 10/03/2022
    100% Design 100% Package Comments to DE 11/01/2022
    25% Design 25% Package Received 07/21/2020
    25% Design 25% Package Comments to DE 10/26/2020
    25% Design 25% Package Received - Resub 1 06/07/2021
    25% Design Design Public Hearing 02/17/2022
    75% Design 75% Package Received 05/16/2022
    75% Design 75% Package Comments to DE 06/29/2022
    Final Design PS&E Received 02/23/2023
    Final Design PS&E Received - Resub 1 03/30/2023
    Final Design PS&E Received - Resub 2 04/27/2023