Planned Federal FY: |
2025 |
Responsible MPO: |
Pioneer Valley Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
CHESTERFIELD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Construction / YOE $10,232,138 STBG / 20.5 TEC / 75% design (A/C 2027 - $4,000,000, 2028- $6,232,138)
|
|
Increase from $4m to $5m and move to 2025 per STIP Action 13
|
|
Increased from $5m to 7,617,776 via STIP Action 17.
|
|
Category |
FA - Surface Trans. Block Grant (STBG) |
|
Federal Cost: |
$6,094,220.80 |
State Cost: |
$1,523,555.20 |
Total Cost: |
$7,617,776.00 |
|
|
|
Planned Federal FY: |
2026 |
Responsible MPO: |
Pioneer Valley Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
CHESTERFIELD
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Construction / YOE $10,232,138 STBG / 20.5 TEC / 75% design (A/C 2027 - $4,000,000, 2028- $6,232,138)
|
|
Move $6,232,138.00 to 2026 and increase to $6,290,549 per STIP Action 13.
|
|
Reduced from 6,290,549 to 3,434,888 via STIP Action 17.
|
|
Category |
FA - Surface Trans. Block Grant (STBG) |
|
Federal Cost: |
$2,747,910.40 |
State Cost: |
$686,977.60 |
Total Cost: |
$3,434,888.00 |
|
|
|
|