Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHESTERFIELD- RECONSTRUCTION OF NORTH ROAD AND DAMON POND ROAD
The project proposes to reconstruct North Road & Damon Pond Road. North Road improvements are proposed from Main Rd (Rte. 143) to the intersection of North Road and Damon Pond Road. Damon Pond Road improvements are proposed from the intersection of North Road and Damon Pond Road to the Goshen town line. The total project length it approximately 2.5 miles. Improvements include full-depth reclamation and multiple culvert replacements along the length of the project, including the culvert at the base of the Damon Pond dam. Horizontal and vertical geometry will be adjusted to improve sight distance and user safety. Finally new pavement markings will be applied within the project limits.
Location:
  • Town of Chesterfield
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2027
    Project Manager: Janhavi Limaye
    Estimated Total Contract Cost: $10,319,259.30
    Estimated Total Federal Participating Construction Cost: $11,290,549.46
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 1
    Current Status: 100% Package Received (as of 07/30/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: CHESTERFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction / YOE $10,232,138 STBG / 20.5 TEC / 75% design (A/C 2027 - $4,000,000, 2028- $6,232,138)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,200,000.00
    State Cost: $800,000.00
    Total Cost: $4,000,000.00

    Planned Federal FY: 2028
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: CHESTERFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction / YOE $10,232,138 STBG / 20.5 TEC / 75% design (A/C 2027 - $4,000,000, 2028- $6,232,138)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,985,710.40
    State Cost: $1,246,427.60
    Total Cost: $6,232,138.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/28/2017
    Project Initiation Form PIF Entered 07/11/2017
    Project Initiation Form PRC Submitted 07/17/2017
    Project Review Committee PRC Approved 07/20/2017
    Project Review Committee Resubmitted 10/02/2024
    Project Management
    100% Design 100% Package Received 07/30/2024
    25% Design 25% Package Received 05/13/2021
    25% Design 25% Package Comments to DE 08/13/2021
    25% Design Design Public Hearing 06/08/2022
    75% Design 75% Package Received 04/11/2023
    75% Design 75% Package Comments to DE 07/12/2023