CHESTERFIELD- RECONSTRUCTION OF NORTH ROAD AND DAMON POND ROAD
The Massachusetts Department of Transportation (MassDOT), along with the Town of Chesterfield proposes a pavement reclamation project that will begin at the intersection of Main Road (Route 143) with North Road, including all of North Road, and extend northeasterly along Damon Pond Road, ending at the Goshen/Chesterfield town line, where Damon Pond Road becomes West Street. The total length of the project is approximately 2.5 miles. The project will include reclamation of the existing roadway to create a new base course and a new hot mix asphalt riding surface. The proposed roadway typical cross section is to consist of two 10-foot lanes with 3-foot shoulders on both sides of the road. The existing roadway width is typically 24- 25 feet on North Road and 22-25 feet on Damon Pond Road. Widening the roadway to a consistent 26-foot width will provide additional area for vehicles, bicycles and pedestrians to share the road. Included in this project is also the demolition and replacement of bridge no. C-12- 022 (5DV) and a 8.5 foot by 6.5 foot asymmetrical corrugated metal culvert at the outlet of the Damon Pond dam. Safety improvements to be implemented as part of the project include shoulder widening, new guardrail, sight distance improvements through clearing where possible along curves, and new warning signs in accordance with the MUTCD.
Location:
  • Town of Chesterfield
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2025/2026
    Project Manager: Janhavi Limaye
    Estimated Total Contract Cost: $10,517,906.48
    Estimated Total Federal Participating Construction Cost: $11,009,508.62
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 1
    Current Status: PS&E Received - Resub 1 (as of 08/20/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: CHESTERFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction / YOE $10,232,138 STBG / 20.5 TEC / 75% design (A/C 2027 - $4,000,000, 2028- $6,232,138)
  • Increase from $4m to $5m and move to 2025 per STIP Action 13
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,000,000.00
    State Cost: $1,000,000.00
    Total Cost: $5,000,000.00

    Planned Federal FY: 2025
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: CHESTERFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Add statewide STBG and TAP per STIP Action 13.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $1,419,424.80
    State Cost: $354,856.20
    Total Cost: $1,774,281.00
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $960,000.00
    State Cost: $240,000.00
    Total Cost: $1,200,000.00

    Planned Federal FY: 2026
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: CHESTERFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction / YOE $10,232,138 STBG / 20.5 TEC / 75% design (A/C 2027 - $4,000,000, 2028- $6,232,138)
  • Move $6,232,138.00 to 2026 and increase to $6,290,549 per STIP Action 13.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $5,032,439.20
    State Cost: $1,258,109.80
    Total Cost: $6,290,549.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/28/2017
    Project Initiation Form PIF Entered 07/11/2017
    Project Initiation Form PRC Submitted 07/17/2017
    Project Review Committee PRC Approved 07/20/2017
    Project Review Committee Resubmitted 10/02/2024
    Project Management
    100% Design 100% Package Received 07/30/2024
    25% Design 25% Package Received 05/13/2021
    25% Design 25% Package Comments to DE 08/13/2021
    25% Design Design Public Hearing 06/08/2022
    75% Design 75% Package Received 04/11/2023
    75% Design 75% Package Comments to DE 07/12/2023
    Final Design PS&E Received 07/07/2025
    Final Design PS&E Received - Resub 1 08/20/2025