Project Description:
BELLINGHAM- REHABILITATION AND RELATED WORK ON ROUTE 126, FROM DOUGLAS DRIVE TO ROUTE 140
The project limits extend from Douglas Drive north approximately 1.60 miles to Mechanic Street. The proposed improvements include pavement rehabilitation – both reclamation and mill and overlay, box widening for shoulder and bicycle accommodations in widened shoulders, installation of 5 foot sidewalks and curbing on one side of the roadway, drainage, utility and street lighting upgrades, as well as new signing and pavement markings. An updated pedestrian crossing signal and approach signage at the mid block crossing at Bellingham Middle School.
Location:
  • Town of Bellingham
  • Construction Begins: Spring 2022
    Resident Engineer: James Kummer
    Construction Bid Price: $5,292,849.82
    District: District 3

    Contracts (1) Progress
    # 117365 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of South Main Street (Route 126) 95% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/27/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/05/2017
    Project Initiation Form PIF Entered 07/05/2017
    Project Initiation Form PRC Submitted 07/13/2017
    Project Review Committee PRC Approved 07/20/2017
    Project Status Advertised 02/12/2022
    Project Management
    100% Design 100% Package Received 10/30/2020
    100% Design 100% Package Comments to DE 01/07/2021
    25% Design 25% Package Received 03/01/2018
    25% Design 25% Package Comments to DE 07/20/2018
    25% Design Design Public Hearing 02/26/2019
    75% Design 75% Package Received 11/14/2019
    75% Design 75% Package Comments to DE 04/28/2020
    Final Design PS&E Received 09/24/2021
    Final Design PS&E Received - Resub 1 11/05/2021
    Final Design PS&E Received - Resub 2 01/07/2022