Project Description: |
GARDNER- RESURFACING AND RELATED WORK ON PEARSON BOULEVARD
The proposed improvements include resurfacing from South Main Street to the Route 2 interchange rotary. Bike lanes will be delineated, and sidewalks will be restored on both sides of the road. An improved pedestrian crossing will be developed at the South Main Street intersection. Enhanced traffic signage will be placed throughout.
|
Location: |
|
Construction Begins: | Autumn 2021 |
Resident Engineer: | Ryan Davison |
Construction Bid Price: | $593,886.22 |
District: | District 3 |
|
Bridges |
|
|
|
|