FRAMINGHAM- TRAFFIC SIGNAL INSTALLATION AT EDGELL ROAD AT CENTRAL STREET
The project involves geometric improvements and installation of a traffic signal at the intersection. The project will also improve pedestrian mobility and safety by providing an exclusive pedestrian phase as well as ADA/AAB compliant sidewalks along both sides of all roadways and crosswalks across all approaches.
Location:
  • Town of Framingham
  • Construction Begins: Autumn 2023
    Resident Engineer: Adam Cline
    Construction Bid Price: $2,496,117.31
    District: District 3

    Contracts (1) Progress
    # 123956 -- Construction Contract
    Traffic Signal Installation at Edgell Road at Central Street

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/17/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/05/2017
    Project Initiation Form PIF Entered 07/05/2017
    Project Initiation Form PRC Submitted 07/13/2017
    Project Review Committee PRC Approved 07/20/2017
    Project Status Advertised 09/02/2023
    Project Management
    100% Design 100% Package Received 09/13/2021
    100% Design 100% Package Comments to DE 11/15/2021
    25% Design 25% Package Received 01/10/2019
    25% Design 25% Package Comments to DE 04/11/2019
    25% Design Design Public Hearing 12/05/2019
    75% Design 75% Package Received 10/13/2020
    75% Design 75% Package Comments to DE 01/21/2021
    Final Design PS&E Received 08/08/2022
    Final Design PS&E Received - Resub 1 05/11/2023