Project Description:
FRAMINGHAM- TRAFFIC SIGNAL INSTALLATION AT EDGELL ROAD AT CENTRAL STREET
The project involves geometric improvements and installation of a traffic signal at the intersection. The project will also improve pedestrian mobility and safety by providing an exclusive pedestrian phase as well as ADA/AAB compliant sidewalks along both sides of all roadways and crosswalks across all approaches.
Location:
  • Town of Framingham
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2023/2024
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $3,058,789.75
    Estimated Total Federal Participating Construction Cost: $3,110,115.00
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 3
    Current Status: PS&E Received - Resub 1 (as of 05/11/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: FRAMINGHAM
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction; CMAQ+STBG Total Cost = $2,484,704; MPO Evaluation Score = 41.
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $1,987,763.20
    State Cost: $496,940.80
    Total Cost: $2,484,704.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/05/2017
    Project Initiation Form PIF Entered 07/05/2017
    Project Initiation Form PRC Submitted 07/13/2017
    Project Review Committee PRC Approved 07/20/2017
    Project Management
    100% Design 100% Package Received 09/13/2021
    100% Design 100% Package Comments to DE 11/15/2021
    25% Design 25% Package Received 01/10/2019
    25% Design 25% Package Comments to DE 04/11/2019
    25% Design Design Public Hearing 12/05/2019
    75% Design 75% Package Received 10/13/2020
    75% Design 75% Package Comments to DE 01/21/2021
    Final Design PS&E Received 08/08/2022
    Final Design PS&E Received - Resub 1 05/11/2023