Project Description:
GARDNER- RESURFACING AND RUMBLE STRIP INSTALLATION ON ROUTE 140
The Route 140 corridor between Green Street and the Winchendon/Gardner town lines was part of an overall larger passing zone evaluation and safety study that examined existing passing zones in relation with vehicle speeds, regulatory and warning signage throughout Winchendon and Gardner. This study resulted in short term low cost safety improvements to mitigate lane departure crashes. The section of Route 140 included in this project was identified as having fair to poor pavement conditions. This project proposes to resurface 1.4 miles of Route 140 under the City of Gardner’s jurisdiction. As part of this project, rumble strip and rumble stripes will be provided, as well as embedded delineators. Drainage structures will be adjusted or reconstructed accordingly, but no changes are proposed to the overall drainage. Guardrail end treatments will be reviewed and revised accordingly.
Location:
  • City of Gardner
  • Construction Begins: Summer 2021
    Resident Engineer: Jeffrey Goyne
    Construction Bid Price: $1,463,409.00
    District: District 3

    Contracts (1) Progress
    # 114900 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 140 (GreenStreet) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/07/2021
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/06/2017
    Project Initiation Form PIF Entered 07/06/2017
    Project Initiation Form PRC Submitted 07/13/2017
    Project Review Committee PRC Approved 07/20/2017
    Project Status Advertised 06/19/2021
    Project Management
    100% Design 100% Package Received 04/21/2021
    100% Design 100% Package Comments to DE 05/13/2021
    25% Design 25% Package Received 04/23/2018
    25% Design Design Public Hearing 03/24/2021
    75% Design 75% Package Received 04/23/2018
    75% Design 75% Package Comments to DE 09/20/2018
    Final Design PS&E Received 05/28/2021
    Final Design PS&E to FAPRO 06/07/2021