Project Description:
BOSTON- MISCELLANEOUS RAMPS MICROSILICA OVERLAY REPLACEMENT ON I-90 & I-93 (CRC 28) CONTRACT 3
Scope of this project includes investigation and analysis, administration, and traffic control to develop a plan to remove defective microsilica wearing surface. It is anticipated that, when this analysis is complete, a construction project will be developed to perform the replacement. The scope includes review of field conditions and inspection documents to develop a condition assessment. In addition, the scope includes the analysis of the structural implications of removing any overlay that is part of the viaduct structural slab.
Location:
  • City of Boston
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Michael C. Haggerty
    Construction Bid Price: $12,736,455.00
    District: District 6

    Contracts (2) Progress
    # 115769 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 123518 -- Construction Contract
    Miscellaneous Ramps Microsilica Overlay Replacement on I-90 & I-93 (CRC 28) Contract 3 4% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/28/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/01/2017
    Project Initiation Form PIF Entered 08/01/2017
    Project Initiation Form PRC Submitted 06/07/2018
    Project Review Committee PRC Approved 06/11/2018
    Project Status Advertised 08/05/2023
    Project Management
    25% Design 25% Package Received 08/10/2018
    75% Design 75% Package Received 03/29/2023
    Final Design PS&E Received 06/12/2023
    Final Design PS&E to FAPRO 07/25/2023