Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
UXBRIDGE- SUPERSTRUCTURE REPLACEMENT, U-02-052, ROUTE 146 RAMP OVER EMERSON BROOK
Location:
  • Town of Uxbridge
  • Construction Begins: Summer 2022
    Resident Engineer: Geoffrey Scannell
    Construction Bid Price: $1,497,349.00
    District: District 3

    Contracts (2) Progress
    # 101631 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide and bridge projects, for the purpose of maintaining Final
    # 118480 -- Construction Contract
    Bridge Superstructure Replacement and Related Work Br. No. U-02-052 (NEXT D Beams), Route 146 Southbound Off-Ramp (Exit 2) over Emerson Brook Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/01/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/21/2017
    Project Initiation Form PIF Entered 09/21/2017
    Project Initiation Form PRC Submitted 09/21/2017
    Project Review Committee PRC Approved 12/15/2017
    Project Status Advertised 06/04/2022
    Project Management
    100% Design 100% Package Received 12/28/2021
    100% Design 100% Package Comments to DE 02/07/2022
    25% Design 25% Package Received 10/05/2020
    25% Design 25% Package Comments to DE 12/28/2020
    25% Design 25% Package Approved 02/04/2021
    25% Design Design Public Hearing 06/17/2021
    75% Design 75% Package Received 08/19/2021
    75% Design 75% Package Comments to DE 10/22/2021
    Final Design PS&E Received 03/11/2022
    Final Design PS&E to FAPRO 05/20/2022