Project Description:
BELMONT- IMPROVEMENTS AT WELLINGTON ELEMENTARY SCHOOL (SRTS)
Location:
  • Town of Belmont
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2021
    Project Manager: David Shedd
    Estimated Total Federal Participating Construction Cost: $1,619,819.84
    Estimated Total Contract Cost: $1,408,647.75
    Funding Provision: This project is planned to be funded through the 2021 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: PS&E Received (as of 02/19/2021 )

    Contracts (1) Status
    # 102485 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide road and bridge projects, for the purpose of mainta Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2021
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BELMONT
    Category: Advertised Projects Constr.
    Budget Section: 2B

    No comments for this TIP line
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,223,577.60
    State Cost: $305,894.40
    Total Cost: $1,529,472.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/12/2017
    Project Initiation Form PIF Entered 10/12/2017
    Project Initiation Form PRC Submitted 05/18/2018
    Project Review Committee PRC Approved 05/24/2018
    Project Management
    100% Design 100% Package Received 09/16/2020
    100% Design 100% Package Comments to DE 11/02/2020
    25% Design 25% Package Received 01/03/2020
    25% Design 25% Package Received 01/03/2020
    25% Design Design Public Hearing 08/17/2020
    75% Design 75% Package Received 01/03/2020
    Final Design PS&E Received 02/19/2021
    Consultant Contract Process NTP Issued 02/20/2019