DISTRICT 4- SCHEDULED AND EMERGENCY BRIDGE DECK REPAIRS INCLUDING JOINTS AT VARIOUS LOCATIONS
Location:
Construction Begins: Winter 2018/2019
Resident Engineer: Christopher Leahy
Construction Bid Price: $1,344,804.00
District: District 4

Contracts (1) Progress
# 105478 -- Construction Contract
Scheduled and Emergency Bridge Deck and Joint Repairs at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/16/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/02/2017
    Project Initiation Form PIF Entered 11/02/2017
    Project Initiation Form PRC Submitted 11/02/2017
    Project Review Committee PRC Approved 12/14/2017
    Project Status Advertised 08/11/2018
    Project Management
    100% Design 100% Package Received 06/04/2018
    Final Design PS&E Received 07/26/2018
    Final Design PS&E to FAPRO 07/31/2018