Project Description:
HUNTINGTON- SYSTEMATIC BRIDGE MAINTENANCE, H-27-019, ROUTE 112 OVER SYKES BROOK
Location:
  • Town of Huntington
  • Construction Begins: Summer 2019
    Resident Engineer: Scott Simonelli
    Construction Bid Price: $489,980.00
    District: District 1

    Contracts (1) Progress
    # 106977 -- Construction Contract
    Bridge Repairs and Related Work Br. No. H-27-019 (Concrete) Route 112 (Worthington Road) over Sykes Brook Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/01/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/14/2017
    Project Need Form PNF Approved 11/09/2017
    Project Initiation Form PIF Entered 11/14/2017
    Project Initiation Form PIF Approved 11/14/2017
    Project Initiation Form PRC Submitted 11/20/2017
    Project Review Committee PRC Approved 12/14/2017
    Project Status Advertised 02/02/2019
    Project Management
    Final Design PS&E Received 06/29/2018
    Final Design PS&E to FAPRO 01/18/2019