Project Description:
WILMINGTON- BRIDGE REPLACEMENT, W-38-003, BUTTERS ROW OVER MBTA
Proposed scope of work includes demolition and full replacement of the existing 3-span timber bridge structure at Butters Row over the MBTA Railroad in Wilmington.
Location:
  • Town of Wilmington
  • Construction Begins: Autumn 2023
    Resident Engineer: Robert Bosy
    Construction Bid Price: $15,615,932.86
    District: District 4
    Current Status: Contractor and utilities are working on obtaining their Railroad Access Permits. (as of 02/05/2024)
    Additional Info: Contractor will install the Railroad Track Monitoring System. Contractor will install construction signage. Contractor will install erosion controls and perform clearing and grubbing operations. (as of 02/05/2024)

    Contracts (2) Progress
    # 123406 -- Construction Contract
    Bridge Replacement, W-38-003, Butters Row Over MBTA 1% Complete
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/15/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractor and utilities are working on obtaining their Railroad Access Permits.
    Additional Info
    Contractor will install the Railroad Track Monitoring System. Contractor will install construction signage. Contractor will install erosion controls and perform clearing and grubbing operations.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/15/2017
    Project Need Form PNF Approved 11/15/2017
    Project Initiation Form PIF Entered 11/15/2017
    Project Initiation Form PIF Approved 11/15/2017
    Project Initiation Form PRC Submitted 11/15/2017
    Project Review Committee PRC Approved 12/15/2017
    Project Status Advertised 07/29/2023
    Project Management
    100% Design 100% Package Received 12/16/2022
    25% Design 25% Package Received 02/25/2021
    25% Design Design Public Hearing 12/01/2021
    75% Design 75% Package Received 06/30/2022
    Final Design PS&E Received 04/14/2023
    Final Design PS&E Received - Resub 1 05/24/2023
    Final Design PS&E Received - Resub 2 06/13/2023